2022 Chip Seal Plan and Status

We expect to start chip sealing each year between late May and early July. The start of the program is dependent on a steady forecast of good weather and completion of road preparation.

Because of the weather uncertainty, we do not schedule dates for each road. We will update the completion dates below as paperwork is processed, which may occur one or more days after the work is completed.

Road name
Last surface
year
Start
milepost
End
milepost
Chip-seal
date
Fog-seal
date
South Bay Ln
1980 0.00 0.40    
Camber Ln
1990 0.00 0.43    
Driftwood Ct
N/A 0.00 0.07    
Twinsview Ct
N/A 0.00 0.11    
Skiff Ln
1990 0.00 0.14    
W Ludlow Point Rd
1980 0.00 0.11    
Fairwind Ct
1990 0.00 0.06
   
Edgewood Dr
N/A 0.00 0.21    
Timber Heights Dr
2003 0.00
0.13    
McKenzie Ln
N/A 0.00 0.07    
Timber Ridge Dr
N/A 0.00 0.12    
Heritage Ln
N/A 0.00 0.10    
Leighbrook Ln
N/A 0.00 0.06    
Timber Meadow Dr
N/A 0.00 0.10    
Cape George Rd
2005 0.00 4.82    
Nelson's Landing Rd
1994 0.35 0.37    
Crutcher Rd
2005 0.00 0.44    
Loftus Rd
2005 0.00 0.49    
McMinn Rd
2004 0.00 0.72    
W Melissa St
2007 0.00 0.12    
W Swaney St
2001 0.00 0.33    
W Maude St
2001 0.00 0.31    
W Kincaid St
1986 0.00 0.29    
9th Ave
2001 0.00 0.29
 
8th Ave
2009 0.03 0.22    
7th Ave
2012 0.00 0.41    
W Price St
2003 0.00 0.114    
W Eugene St
2003 0.00 0.12    
Anderson St
2003 0.00 0.12    
10th Ave
2003 0.00 0.13    
9th Ave
2003 0.00 0.05    
West Valley Rd
2002 2.30 5.56    
Gibbs Lake Rd
2005
0.00 0.74    
W Egg & I Rd
2000 0.00 0.44    
Egg & I Rd
2000 0.00 0.73    
Country Ridge Dr
2001 0.00 0.28    
Blue Mountain Rd
2001 0.00 0.51    
Lindsay Hill Rd
2001 1.93 3.33    
Broad Spit
2001 0.00 0.32    
Leland Valley Rd W
2021 2.48 4.13 Fog seal only